Home Additions in Los Altos Hills

Acre lots, and a site permit before the building permit

Homes in Los Altos Hills sit in the Residential Agricultural district: a one-acre floor on lot size, a single primary home per parcel, and a countryside character close to Woodside’s or Portola Valley’s. Room to grow is seldom the issue. The order of approvals is. Before the Building Department will take your plans, Planning has to sign a site development permit covering what the work does to the land, and every addition, large or small, needs one. We run both stages for you, and the building permit is held under our CSLB license #1101484.

Room additions that follow the contours

Planners here judge a new room by how it sits on the land: whether it rides the natural slope, how much soil it disturbs, how it reads from the road. Where the ground falls away, the Town would rather see stepped footings than tall walls, so a family room or a guest wing may land a few stairs below the main floor.

Building a second floor

Going up counts as an exterior change, so the land review applies here too. A project planners can approve themselves usually gets an answer in about a fortnight; one that requires a noticed hearing is typically heard three or four weeks in, on a Tuesday morning, after letters go to every property within 500 feet.

Kitchen and dining additions

A kitchen remodel inside the walls is one of the Town's smaller permits, sent by email with drawings. Once the kitchen pushes into new floor area it becomes an expansion, with site development review first.

Guest suites and ADUs

On an acre there is often room for a separate unit as well as the main house. If the new space needs its own kitchen, see our Los Altos Hills ADU page; the Town's ADU rules are a different path from an addition.

Garden rooms and covered terraces

New paving counts as well: a deck or terrace is reviewed with the same care as a room. The ember-resistant strip the Town wants in the first five feet around a house decides what can be built right against the walls.

Primary bedroom wings

An owners' wing: sleeping room, bath and closet at one end. More fixtures raise the sewer question: a major addition has to tie into the public line, with few exceptions, and on lots with no line inside 200 feet, septic approval comes from Santa Clara County instead.

Site development review is the Planning Department’s look at what a project does to the land. It covers any exterior alteration or enlargement of a house, to every new building, and even to new decks and patios. It opens with a required site analysis session with a planner to analyze the site, which the Town requires before it will accept an application, and a major addition can also be sent to the Town Geologist with a soils report.

Three speeds of review

The Town’s FAQ describes three tracks. Projects staff can decide alone typically come back in about two weeks. Projects that require public notice are heard at a Site Development hearing roughly three to four weeks in. Projects for the Planning Commission are often heard six to eight weeks in, after all the other agencies have signed off. Both the Fast Track and the Site Development hearings sit on Tuesdays at 10.

What the reviewers look at

Fit with the land and the street, respect for the natural grade, and how the plan deals with soils, slope, creeks and swales. Steep ground over roughly 30 percent, heritage oaks and creek corridors can be placed under an open space easement. Two conditions come with almost every major addition: a screening landscape plan, checked once framing is done, and exterior lights that are shielded and aimed down.

Fire

At its wildfire workshop in April 2025 the Town described clearing 100 feet around a home and keeping the first five feet ember-resistant at the house, and noted it cannot reduce the hazard levels CAL FIRE sets. We check where your parcel falls on the state map before picking roof, vents and siding.

Our nearest work

Down the hill in Los Altos we completed a whole-home remodel, and in Woodside a backyard ADU we are building is nearly finished. Our closest finished addition is in Santa Clara, a new garage with an office.

Key Consideration on a Los Altos Hills acre

  • Site development first

    Planner meeting, then the land permit, then building plans: the Town will not take them in a different order, so we plan the design calendar around that sequence.

  • Architectural Compatibility

    The reviewers' question is fit: with the land, with the neighborhood and with the house. A low addition that steps with the slope usually answers it better than a tall one.

  • Geology and foundations

    A major addition may go to the Town Geologist with a soils report, and the footings follow its findings. On a slope, the Town would rather see the foundation step down than stand on tall walls.

  • Fees and the fixed price

    The building fee table the Town still links, from FY 2023/24, is $240 plus 0.9% of the job's valuation. Our part is a fixed written price after a site visit, exclusions spelled out.

  • Sewer, septic and fire

    A major addition must connect to sewer with limited exceptions; septic is a county permit. Defensible space and an ember-resistant zone set the materials at the walls.

Town permits for a Los Altos Hills addition

Paper plans are gone in Los Altos Hills: since mid-2024 every building permit has been filed through eTrakit. The Building Department checks code and inspects; the Planning Department issues the land-use approvals, site development and zoning, that must come before it.

  • Building Permit

    Submitted through eTrakit once the land permit is in hand.

  • Grading Permit

    Kept to a minimum by design, since reviewers look for additions that follow the natural contours.

  • Electrical Permit

    For the new rooms' circuits and outdoor lighting, which the Town's standard conditions require to be shielded and pointed down.

  • Plumbing Permit

    For new fixtures, and a sewer connection where a line is within 200 feet or the addition is major.

  • Mechanical/HVAC Permit

    For extending heating and cooling to the new space.

  • Zoning Permit

    The land permit, decided by staff, at a noticed hearing, or by the Planning Commission.

  • Environmental Permits

    Open space easements on steep slopes, heritage oaks and creeks; septic approval from the county where there is no sewer.

Fridays have no inspections in Los Altos Hills, and the Town wants three to four days’ notice, so our requests go in early in the week. Our crews can be on site 8:00 to 5:30, six days a week, but heavy machines stay off on Saturdays. The screening landscape plan is checked after framing, and we close the permit at the final.

Frequently Ask Question

Yes. Los Altos runs design review of the house; Los Altos Hills runs site development review of the land as well, requires a planner meeting before you apply, and may send a major addition to the Town Geologist. The lots are larger too, with a one-acre minimum.