Project · Menlo Park, CA

A Menlo Park kitchen, laundry and powder room: a project from February to April 2026

White shaker cabinets, quartz from the counters up to the window, a wood island with the cooktop in it, and the laundry room and powder room beside the kitchen, all photographed by our crew as it was built.

A finished kitchen in Menlo Park: white shaker cabinets, a wood island and stainless wall ovens
WhereMenlo Park, CA
WhatKitchen, laundry room and powder room
WhenFebruary to April 2026
StatusCompleted

This kitchen runs the length of the house: tall white shaker cabinets with a pair of stainless wall ovens at one end, a sink under the window with quartz carried up the wall behind it, and a wood island in the middle with the cooktop set into its quartz top.

The same job covered the laundry room off the kitchen, with new cabinets and a quartz counter over the machines, and the powder room next to it, with a new vanity and lighting.

Our crew photographed the work every month. February was cabinets, with every floor covered. March was stone: the quartz counters, the cooktop, the powder room vanity and the island’s wood cabinets. The kitchen was finished in April.

The finished rooms

The full length of the finished Menlo Park kitchen, from the wall ovens to the sink window
A cooktop set into the quartz top of the island, white cabinets and a stainless refrigerator beyond
The sink under the window, with quartz carried up the wall behind it
Stainless double wall ovens and a refrigerator set into tall white cabinets
The wood island with shaker doors and brushed handles, under a white quartz top
The sink wall: white upper and lower cabinets, a stainless dishwasher and quartz backsplash
The laundry room off the kitchen, with new white cabinets and a quartz counter beside the machines
The powder room with a new white vanity, a framed mirror and a light above it
Close up of the undermount sink and the veined white quartz backsplash

How it was built, month by month

February 2026

Cabinets go in: the tall oven cabinets, the sink run and the base of the island, with the floors covered throughout.

February: the tall oven cabinets installed, the floor covered with protection board
February: the sink run of white cabinets set, before the counters
February: the base of the island being built, with the plans laid on top
March 2026

Stone and finishes: the quartz counters under protective tape, the powder room vanity, then the cooktop and the island’s wood cabinets.

March: the new quartz counters in, edges protected with blue tape
March: the powder room vanity and faucet installed, walls patched for paint
Late March: the island's wood cabinets in place and the kitchen nearly finished