Project · Union City, CA

Jia Chen and Chris’s front addition and two bathrooms in Union City, from May to August 2026

Roughly 320 to 330 square feet added across the front of the house, with skylights and new floors, and both bathrooms rebuilt, finished at the end of August on the three to four months the family was given, and photographed by our crew as it was built.

The finished addition in Union City from the front: light blue stucco, a black front door with a glass sidelight, two windows and a new wooden step
WhereUnion City, CA
WhatHome addition and two bathrooms
WhenMay to August 2026
StatusCompleted

The project started with the idea of a home office and more square footage, in a house whose front yard, in the family’s words, was a lot of wasted space they never used. The plan built an addition across the front of the house, out past where the front wall and the porch had been, and rebuilt both bathrooms at the same time, with the family living in the house throughout.

The addition added roughly 320 to 330 square feet: a bright room with a new front door, skylights and a ceiling fan that opens straight into the dining area and the kitchen, and a room set up as an office with two windows. Outside, the house was stuccoed and painted light blue, with a new wooden front step. The guest bathroom has a green tiled walk-in shower behind a glass door with a pebble floor; the primary bathroom has a navy tiled shower wall with a rain shower head and a long niche.

Our crew photographed the work as it went. In May the old porch came off and both bathrooms were stripped and waterproofed. June was the foundation forms for the addition and the first tile. July was framing, the roof, windows and house wrap, then the first coat of stucco, and by the middle of July the guest bathroom was in use. August was flooring, paint and the finished rooms, photographed on 27 August 2026. Ray had told the family three to four months from start to finish, and it finished at the end of August.

Jia Chen and Chris, in their own words

Jia Chen's Home Addition & Renovation Reveal in Union City, Final EpisodeJia Chen’s Home Addition & Renovation Reveal in Union City, Final Episode

“He was saying three to four months from the start to the end. And it did. We finished end of August. Just like he said.”

Jia Chen and Chris, the timeline

“I liked that they had guys that they can pull from other jobs. You know, if they needed more manpower, they had more manpower the next day.”

Jia Chen and Chris, how the crew kept pace

“It feels like we’re like in a hotel or a resort or a spa using our bathroom.”

Jia Chen and Chris, the guest bathroom, in July

“You guys treated our house with respect and love and you guys did a great job.”

Jia Chen and Chris, the crew

The finished addition and bathrooms

Inside the addition: a light room with wood-look floors, the new front door between two windows and a skylight overhead
The addition opening into the dining area and the kitchen, with a skylight, a ceiling fan and a new interior door
A room in the addition set up as an office, with a desk under two windows and wood-look floors
The guest bathroom: a green tiled walk-in shower behind a glass door, a pebble shower floor, a black vanity and open shelves
The primary bathroom shower: a navy tiled wall with a rain shower head, white tile, a long niche and a stone mosaic floor
The addition from above: light blue stucco walls, the front door and step, and skylights set into the roof

How it was built, month by month

May 2026

The old porch came off, its roof held on temporary posts, and both bathrooms were stripped and waterproofed.

May: the front of the house before the addition, the porch removed and its roof held on temporary posts
May: a bathroom stripped and coated with red waterproofing around the shower
May: the shower wall and window of a bathroom under red waterproofing
June 2026

Foundation forms for the addition across the front, and the first tile going up in the guest bathroom.

June: wooden foundation forms laid out across the front of the house
June: the foundation forms for the addition seen from the side of the house
June: green tile going up on the guest bathroom shower walls
July 2026

Framing and the roof, windows and house wrap, then the first coat of stucco. The guest bathroom was finished and in use by mid July.

July: the addition framed on its new floor, with the roof rafters overhead
July: the addition's front wall in house wrap and wire lath, with the windows and the door opening set
Late July: the first coat of stucco on the addition, with the windows still masked
August 2026

New flooring through the addition, paint, the shower glass, and the finished rooms photographed on 27 August.

August: the new wood-look floor down through the addition, under the skylight and the ceiling fan
August: the guest bathroom shower with its glass door, green tile and pebble floor